|

General
Description
The 12.5km-long MTR
Tseung Kwan O Extension is a HK$18 billion project which provides an extension
line from the existing station of Lam Tin in Kwun Tong to the new town
of Tseung Kwan O serving a population of about 180,000 in the district.
The new line comprises
of 5 stations, namely the Yau Tong, Tiu Keng Leng, Tseung Kwan O, Hang
Hau and Po Lam Stations. In addition, a further extension will be provided
in a few years' time from the Tseung Kwan O Station to a new station at
the eastern end of the new town which serves also as the depot of the
Tseung Kwan O Line. Residential development with more than 20000 housing
units will be provided around this depot area.
The civil work of
the project subdivided into 13 main contracts with the first contract
commenced in November 1998. The line was put into full operaion in August
2002.
The
alignment
The alignment of the
line starts immediately from the existing station of Yau Tong eastward
through a 1.2km-long drill-and-blast tunnel and another 300m cut-and-cover
tunnel before reaching the Yau Tong Station. Immediately leaving the Station,
the rail cuts into another 2.2km-long drill-and-blast tunnel (Black Hill
Tunnel), the outlet of which joins almost to the station structure of
the Tiu Keng Leng Station. Further to the eastern direction, a section
of 0.9km long cut-and-cover tunnel links between the station of Tiu Keng
Leng and the adjoining Tseung Kwan O Station on the newly reclaimed land
of Tseung Kwan O Bay. Leaving the Station, the alignment continued in
another 1.8km-long section of cut-and-cover tunnel which heads slightly
northwestward into the Hang Hau Station. Finally, through the final section
of 1.4km-long cut-and-cover tunnel, the line reaches its terminal station
at Po Lam.
The extension to
the depot comprises of a section of 0.8km cut-and-cover tunnel which branches
off from the approach tunnel about 0.6km eastward from the Tseung Kwan
O Station. The alignment of this extension then cuts into the Pak Shing
Kok hill through a 2.0km-long drill-and-blast tunnel and reaches its eastern
portal, which serves also as the entrance to the depot facilities.
Construction
Features of the Major Work Portions
Due to the massive
scale of works involved in the extension line which can hardly be discussed
in detail under the context of this article, the writer will focus only
on some construction features of the major work portions along this
12.5km-long rail line, as follow.
- Tunnel between Lam Tin
and Yau Tong Station
The existing
Kwun Tong Line links to the Tseung Kwan O Extension Line directly
through a 1.2km-long drill-and-blast tunnel cutting from the eastern
end of the station structure of Lam Tin towards Yau Tong. The tunnel
is in twin-tube design with one track slightly located on top of the
other to convenient the interchanging arrangement provided in the
Yau Tong Staion. Tunnel portal is situated in the western end with
access ramp for the handling of equipment and excavated spoil (Photo
1).
- Yau Tong Station
The station situates
in a shallow trough which is formed by cutting into a solid rock terrace
averaged 12m above the nearby level (Photo 2 and 3). Since the contract
involved the formation of the undulating ground around Yau Tong Road
and Cha Kwo Ling Road with area more than 12 hectares (Photo 4 and
5) a temporary pier facility (Photo 6) was set up in the nearby Kwun
Tong Tsai Bay for the dumping of the excavated spoil. The box-shaped
station structure measures about 450m x 50m (Photo 7, 7a, 8 and 9),
with the track and passenger platform built on the formation level
(about 12mPD) and the entrance concourse at an elevated podium structure
25m above. Besides serving as an interchanging station to the Island
Line, there are also provisions of pedestrian footbridges leading
to the nearby Yau Tong Estate (Photo 10).
- Approach tunnel linking Yau Tong Station and the Eastern Harbour
Crossing
The Tseung Kwan
O Line connects into the Island Line through the existing track within
the Eastern Harbour Crossing (EHC). The 0.8km-long approach tunnel is
slightly curved in a 600m radius, linking the Yau Tong Station to the
tunnel approach of the EHC. This section of tunnel comprises of three
major sub-sections, including the approach section leading to the Yau
Tong Station (Photo 11), a cut-and-cover tunnel section formed in the
rocky sub-soil of the nearby ground (Photo 12 and 13), and a merging
section joining into the existing tube of the EHC (Photo 14). Provision
of ventilation facility is located on top of the approach tunnel near
the merging section (Photo 15). Complicated phasing requirement is introduced
in the construction process, especially when doing the section approaching
EHC where traffic diversion is required in order to allow the tunnel
to cut into the side of the EHC vehicular approach (Photo 16).
- Black Hill Tunnel (located between Yau Tong and Tiu Keng Leng Station)
Due to spatial
constraint, this 2.0km-long tunnel fits almost the entire alignment
between the Yau Tong and Tiu Keng Leng Station, leaving less than 300m
on each side (Photo 17 and 18) as approach before joining the station
structures. In addition, the track arrangement in the stations in particular
to cater for the interchanging requirement merging to various Lines,
further complicates the tunnel configuration and alignments. As a result,
the provision of the tunnel portals and the teething arrangement with
the station contracts became very difficult.
The tunnel alignment
is arranged in a four-tube configuration at the two ends abutting
the approach section. It then converts into two-tube arrangement in
the centre section (Photo 19). A 20m diameter service shaft (Photo
20) was also provided in the southeastern end of Lei Yue Mun Road
for emergency, ventilation and material access purposes.
- Tiu Keng Leng Station
The Station
situated partly on the previous Tiu Keng Leng village and partly on
the formed land by cutting into the rocky slope in the neighborhood
around (Photo 21 and 22). The station formation process involved the
cutting and removal of more than 1600000m3 of spoil mainly in solid
rock, which includes the forming of a 480m x 55m x 20m deep rock trough
(Photo 23) to house the underground portion of the station structure.
The four-level underground structure was directly seated on raft on
the formed trough and constructed using bottom-up method (Photo 24).
The lower 2 levels are used as the passenger platform in double-deck
arrangement for interchanging purpose for the Kwun Tong Line and Tseung
Kwan O Line. The contract also included the construction of a ground
transportation and passenger interchanging facility (Photo 25) and a
600m section of cut-and-cover tunnel heading to the Tseung Kwan O Station
direction.
- Tseung Kwan O Station
The Station
situated in a newly reclaimed land with provision for a ground transportation
and passenger interchanging facility that covered an area about 5 hectares
in size (Photo 26). Except for the entrance concourse, majority of the
station structure is buried underground. The Station was constructed
using bottom-up arrangement (Photo 27, 27a and 28) within a gigantic
trench lined with diaphragm wall on both sides and supported with truss-form
standard strut members. The contract also included the construction
of the ground transportation facilities (Photo 29) and two sections
of approach tunnel on both ends of the station. The approach tunnel
was constructed using bottom-up arrangement similar to the station,
but with several locations at existing road junctions using top-down
arrangement in order to provide undisturbed traffic at the ground level.
- Hang Hau Station
The Station situated in a reserved land within the center of a cluster
of densely populated private housing estates (Photo 30). Majority of
the station structure, including the 120,000 m2 ground transportation
facility, was constructed underground (Photo 31). The 16m-deep main
station structure was constructed using top-down arrangement (Photo
32) for this method could assure the least disturbance caused to the
surroundings during the excavation process. While the 9m-deep transportation
facility was built in bottom-up manner (Photo 33) due to the reason
of minimizing cost. The approach tunnel at both ends of the station
cut across two existing roadways at the ground level, which was thus
constructed using top-down arrangement with the minimal disturbance
caused to the surface traffic.
- Po Lam Station
This Station
is the terminal station of the Tseung Kwan O Line (Photo 34). The box-sectioned
tunnel (Photo 34a) for the rail track ascends slowly after leaving the
Hang Hau Station and levels to ground surface before reaching the station
of Po Lam (Photo 35). The station structure is built at grade with bored
piles as foundation, (Photo 36). The superstructure measures about 380m
x 40m, with the passenger platforms located on the ground level (Photo
37).
- The Depot
The Depot, including the nearby areas for
future development, is located on a 26 hectares reclaimed land (Photo
38) in the southeastern corner of the new town of Tseung Kwan O. Besides
serving as the maintenance depot of the line, the depot is provisioned
to accommodate residential development to house about 20000 residential
units at its final stage. The depot structure is a one-level podium
deck, about 25m above ground, with minor structures scattered underneath
to provide logistics, services and support for the maintenance of the
train (Photo 39). The layout of the depot structure is basically in
column and transfer beams (Photo 40) arrangement with span ranging from
12m to 30m. Method of construction is rather traditional, all structures
are cast-in-situ (Photo 41), with foundation using bored piles on isolated
rafts and stiffened with tie beams (Photo 42), rectangular-sectioned
steel form for columns (Photo 43), panel form for transfer beams, and
plywood soffit supported on I-beam joist and propped for the deck structure.
Majority of the transfer beams were post-tensioned, and with some built-in
services trough decked with precast panels. Starter bars were provided
over the podium deck for linking to the superstructures of the future
residential development.
- Pak Shing Kok
Tunnel (located between half way of Tseung Kwan O Station and Hang Hau
Station, and the Depot)
This
is a drill-and-blast tunnel excavated in extremely hard volcanic rock.
The tunnel is in twin-tube design with branching-off into four at the
eastern portal when approaching to the depot entrance. After blasting
and treatment to the exposed rock surfaces, a smoothing layer of shotcrete
was applied as the underlay (Photo 44), before the installation of the
waterproofing membrane (Photo 45 and 46), and the placing of the 250mm
thick lining using Grade 40 mass concrete. A 12m long shutter form was
used to construct the tunnel lining (Photo 47). The shutter was set
up on short length of rails in order to move the form easily to the
onward work position. The final finishing of the
tunnel interior can be seen in Photo 48 and 49.
- Cut-and-cover
tunnel in general
Cut-and-cover tunnel forms a major part of the rail alignment in the
Tseung Kwan O Line. Majority of the cut-and-cover tunnel was constructed
in the newly reclaimed land in the previous Junk Bay (Photo 50). The
tunnel was basically in standard box-section, measure 14m x 8m in average,
with structural partition wall in the center to form two separated tubes.
Some tunnel sections are double-decked for platform interchanging purpose
(Photo 50a), as in the approaches to the Yau Tong, Tiu Keng Leng and
Tseung Kwan O Station.
Excavation of
the tunnel was done in bottom-up manner, with side support using diaphragm
wall, or for some shallow or non-typical sections, using sheet pile
or pipe pile wall (Photo 50b, 50c and 51). Ground water control is
a crucial problem in most situations for a large portion of the sections
are located in made ground with some laid less than 20m from the seawall
(Photo 52 and 53). For the tunnel structure, a travel-type tunnel
formwork system was used in the construction (Photo 54 and 55), with
some non-typical sections employing usual large-panel type shutter
form (Photo 56 and 57).
Summary
As an overall
summary, the followings are some interesting figures/facts that may provide
readers a fuller understanding of the works involved in this gigantic project.
- Composition
of work along the alignment:
| Drill-and-blast
tunnel |
5.4
km |
| Cut-and-cover
tunnel |
4.2
km |
| Stations,
junctioning and approach sections |
2.9
km |
- Ground/sub-soil
condition and earthwork involved in the major work portions
|
Major
work segment
|
Ground/Sub-soil
condition
|
Work
involvement
|
Approximate
quantity
|
| Formation
of the Cha Kwo Ling and Yau Tong area |
Mainly volcanic
rock |
Formation
of the nearby undulating foothill into terraced ground for the
station structure of Yau Tong and to provide land for future residential
developments.
|
Land area
involve: 12 hectaresExcavation: 1400000 cube metre |
| Yau
Tong Station |
Volcanic
rock |
Forming
a shallow trough for the housing of the station structure
|
Excavation:
120000 cube metre |
| Black Hill
Tunnel |
Volcanic
rock |
Forming
of the drill-and-blast tunnel and a service portal
|
Excavation:
150000 cube metre |
| Formation
of land for Tiu Keng Leng and Tsung Kwan O Station |
Mainly volcanic
rock |
Formation
of the previous Tiu Keng Leng Village to provide leveled land
for the Tiu Keng Leng Station, as well as to form new land by
reclamation for the Tseung Kwan O Station. The works also included
the provision of land nearby the stations for residential or related
development purposes.
|
Total areas
of land formed: 28 hectaresExcavation (by rock cutting): 1600000
cube metre |
| Tiu Keng
Leng Station |
Volcanic
rock |
Forming
a rock trough for the housing of the station structure
|
Excavation
: 550000 cube metre |
| Tiu Keng
Leng Station |
Volcanic
rock |
Forming
a rock trough for the housing of the station structure
|
Excavation
: 550000 cube metre |
| Tseung
Kwan O Station |
Made
ground |
Forming
of the station structure using bottom-up method
|
Excavation:
280000 cube metre |
| Hang Hau
Station |
Made ground |
Forming
of the underground station and ground transportation facility
structure
|
Excavation:
800000 cube metre |
| Po Lam Station |
Made ground |
Cutting
down of the surface soil to form the rafts of the station structure
|
Excavation:
20000 cube metre |
| Pat Shing
Kok Tunnel |
Volcanic
rock |
Forming
of the drill-and-blast tunnel and portal facilities at both ends
|
Excavation:
130000 cube metre |
| The Depot
and the related development |
Made ground
and partly decomposed rock |
Formation
of land for depot and related residential development purpose.
General excavation by cutting down of the surface soil to form
the rafts for the construction of the depot structure |
Total newly
formed land: 26 hectaresGeneral excavation: 100000 cube metre |
|