| THE
CONSTRUCTION OF
A SEMI-BURIED BUILDING - A SUPER-SIZED SHOPPING MALL: THE FESTIVAL WALK |
| Raymond
Wong Wai Man, Division of Building Science and Technology, City
University of Hong Kong SYNOPSIS The Festival Walk, situated on a 21,000 sq m site on a stump of a small hill at the base of Beacon Hill in Yau Yat Chuen, is one of the most difficult building construction job in recent Hong Kong. The project has experienced considerable amount of complications during the course of its construction, basically inherited from the special nature of the job. This includes, such as, its unfavorable topographical and geotechnical environment, working within the railway and tunnel lines of two very busy railway networks, the requirements of constructing a very large building with exceptionally deep basement, the involvement of very high ceiling headroom and long span, as well as some access problems which is quite common for sites of this size, complexity and scale. Since the overall involvement of works in the Festival Walk project was enormous, this paper serves to provide a technical summary to the major elements and operations of works involved throughout the entire project, with emphasis mainly on the construction and engineering aspects. KEYWORDS Site formation, hydrafraise, top-down basement construction, complicated phasing arrangement, long span structure. 1. Topography and Geology of Site The site is situated on a narrow terraced strip of land along the Tat Chee Avenue, which measured about 290m x 80m in size. The existing ground levels vary from +29m PD1 to +36m PD along the west boundary on Tat Chee Avenue side, and from +19m PD to +26m PD along the east boundary on the Kowloon Canton Railway (KCR) Kowloon Tong Station side. In order to cope with the aerial height restriction requirements and to achieve the development potential allowed under the condition of sale of the site, there is four levels of basement and three levels of semi-basement in the development, with the deepest level being some 36m below Tat Chee Avenue. As a result, a very large amount of soil and rock had to be removed for the construction of the basement. Sub-soil conditions were in general not too favorable for the Festival Walk project. Completely decomposed granite was encountered at ground level, with the presence of many corestones. Rockhead on the Tat Chee Avenue side varied between 6m to 65m deep (Figure 1). At the northern portion of site, bedrock was very close to the surface, but sloping downward to about 60m deep near the KCR Kowloon Tong Station. Ground water level varied across the site, with a flow consistently to the southeast or downslope direction. The Mass Transit Railway (MTR) tunnels run directly through the centre of the site, thus confined the geometrical design of the sub-structure. As a result, the lowest excavation levels to the north and south of the tunnels are at -1m PD and +8m PD respectively, with the section above the MTR tunnels not exceeding +13m PD so as to ensure at least 3m cover above the tunnel structures. 1 Principal Datum
2. Site Formation and Diaphragm Wall Construction
Since chiseling was not allowed within 10m of MTR tunnels, "stitch drilling" was used to overcome underground obstructions before the forming of the cut-off diaphragm walls (Photo 2). This was done by drilling a series of 600mm diameter holes in row, so that any boulder or corestone could later be cut into fragments small enough to be removed by grab. Site formation works were carried out in roughly 6 phased, unsymmetrical sections, according to the convenience of cutting and dividing of the complicated building layout with construction jointings. The main strategy in the scheduling of site formation was to have the northern portion completed as the earliest possible, so that it could be handed over to the main contractor for the construction of the basement and superstructure on this portion. The reason was in fact straight forward, a circular ramp leading to the basement carpark would be located here. With the circular ramp completed, it could be used as the access for vehicle to enter into the basement which was constructed using top-down method. This would be critical, for without which, the last phase of formation on the southern tip of site could not be carried out in full scale (Photo 3). As by that time, the only entrance/exit into the site was still in the southern tip.
3. Bored Pile Foundation In the northern part of site where an office block was to be constructed above the podium structure, hand-dug caissons of 3.25m diameter were employed, so as to produce a series of large diameter piles to take up the huge superimposed loads. Steel stanchions were later installed onto the top of piles as support to the basement structure during its construction using the top-down method.
As for all top-down basement construction, the first floor slab to be constructed on grade is important for it signifies the commencement of the basement work by providing the separating plate and lateral tie such that basement excavation can be started from there on. For the Festival Walk project, this first plate was on the +19.5m PD level (Photo 5). From this entrance point, excavation to the basement and the construction of the semi-basement structure above the +19.5m PD plate had proceeded simultaneously according to the preliminary 6-phased arrangement, again, in staggered sections that joined with carefully located construction jointings. For the lowest 4 levels of basement where headroom averaged at 3.1m that used as parking spaces for private car, part of which were excavated and constructed using a "Double Bit" method2. This could produce a higher headroom such that excavation could be done using normal-sized excavating machines, as well as to allow the entrance of dumping vehicles for removal of spoil. To provide the required protection to the MTR tunnels and to prevent heaving while large volume of soil were being removed, some of the basement slabs, especially those around the MTR tunnels, were deliberately thickened for the purposes. In views of large amount of structural jointings were required to match with the complicated phasing arrangement, this made the casting process rather difficult and time-consuming (Photo 7). 2 Please refer to item 4 of reference There were some locations where the progress of the basement construction works had been significantly interrupted. At the northern edge and the adjoining corner along the Tat Chee Avenue where the rockhead was laying shallowly well above the final formation level of the lowest basement, the toe of the diaphragm wall panels had to be extended further downward during the top-down construction until it reached the final level below the lowest basement. This was done by in-situ underpinning method. Sections of the diaphragm wall panels were constructed after the removal of the bedrock, layer by layer, with vertical junctions being connected by the provision of steel couplers. In order to minimize the delay caused by the cutting of large volume of hard rock and the associated underpinning works to the toe of diaphragm wall, a section of basement which measured about 100m x 15m along the mid-northwestern corner of Tat Chee Avenue, was being isolated as the 7th portion in the basement construction process (Photo 8). To allow for the continual progress to the upper structure and to stabilize the effect of isolating this part of the basement structure, a row of structural steel strut was erected, which provided the lateral support between the diaphragm wall and the base plate at the +19.5m PD level. The third area of interruption came from the works around the MTR pedestrian entrance and ventilation shaft. This sensitive structure of the MTR was initially protected by a row of in-site bore piles. A 4-layered temporary steel strut and shoring system was erected to stabilize the structure while excavation proceeded (Photo 9).
5. The Main Structure The phasing arrangement of the main structure also followed the 6-phased concept, but with flexible refinements into numerous sub-phases according to the actual progress or practical completion of the consequent sections, or according to the availability of access or spaces into the scheduled work spots (Photo 11).
There were 7 pieces of 48m-span beams above the void of the ice skating rink. These beams were simple-supported in design, cast in-situ and sat on structural bearers on top of columns on each end. The beams were further tied by a 3.5m deep transverse beam on which the southern portion of the 4-level office block was supported. All beams were post-tensioned in order to enhance their structural performance as well as to reduce their size and weight (Photo 12). The main frame of the skylight composed of eight unidentical structural steel trussed girders, each with ends simple-supported and stabled by bolts to the seating plate that anchored firmly in the concrete of the side wall (Photo 13). The girders were erected from the sides outward, producing two cantilevers at the beginning, but supported temporary by tubular props, until the two sides met in the middle. Steel beams running from girder to girder direction were erected afterward to fill up the space in-between.
There were four main glass wall units on the east and west elevations of the building, totally with a glazed area of about 3500 sq m. Two of the glass wall units were of full height stretching from ground to roof that bounded the atrium space of the "Canyon". The wall units leaned slightly outward at 100o and 93o respectively at the east and west facing elevations. The main frame of the glass wall was constructed in box-sectioned steel of varied sizes, with some member deliberately being tilted to provide added architectural interest (Photo 14). |